Hugo to Valliant 345 kV Transmission Line and Substation

Project Timeline

  • January 2009 -- Project approved in Southwest Power Pool Transmission Expansion Plan and Notice to Construct issued
  • April 2009 -- Project assigned to ITC Great Plains
  • October-November 2009 -- Community leader briefings
  • December 7-8, 2009 -- Community Open Houses in Fort Towson and Valliant
  • January-July 2010 -- Landowner meetings and right-of-way acquisition
  • April-July 2010 -- Substation engineering design
  • July-October 2010 -- Tower line engineering design
  • First Quarter 2011 thru Second Quarter 2012 -- Substation and transmission line construction
  • April 1, 2012 -- Substation and transmission line in service