Project Timeline
- January 2009 -- Project approved in Southwest Power Pool Transmission Expansion Plan and Notice to Construct issued
- April 2009 -- Project assigned to ITC Great Plains
- October-November 2009 -- Community leader briefings
- December 7-8, 2009 -- Community Open Houses in Fort Towson and Valliant
- January-July 2010 -- Landowner meetings and right-of-way acquisition
- April-July 2010 -- Substation engineering design
- July-October 2010 -- Tower line engineering design
- First Quarter 2011 thru Second Quarter 2012 -- Substation and transmission line construction
- April 1, 2012 -- Substation and transmission line in service