Phase I Project Timeline - Spearville to Knoll

  • December 9 & 10, 2008 -- Community Open Houses
  • March 13, 2009 -- File Siting Application with The Kansas Corporation Commission (KCC) for Spearville to Knoll segment
  • April 2009 -- Project approved in Southwest Power Pool Balanced Portfolio for cost recovery/allocation
  • July 13, 2009 -- KCC approved ITC Great Plains' Phase I siting application
  • July 2009 thru October 2010 -- Right-of-Way Acquisition and Engineering Design
  • First quarter 2011 thru May 2012 -- Line Construction
  • June 2012 - Energize Transmission Line from Spearville to Knoll