Our Projects
- December 9 & 10, 2008 -- Community Open Houses
- March 13, 2009 -- File Siting Application with The Kansas Corporation Commission (KCC) for Spearville to Knoll segment
- April 2009 -- Project approved in Southwest Power Pool Balanced Portfolio for cost recovery/allocation
- July 13, 2009 -- KCC approved ITC Great Plains' Phase I siting application
- July 2009 thru October 2010 -- Right-of-Way Acquisition and Engineering Design
- First quarter 2011 thru May 2012 -- Line Construction
- June 2012 - Energize Transmission Line from Spearville to Knoll
|

|

|
|