Spearville to Knoll to Axtell (KETA) Project
- April 2009 -- Project approved in Southwest Power Pool Balanced Portfolio for cost recovery/allocation
- August 26, 2009 -- Community Action Group meeting
- November 30-December 1, 2009 -- Community Open Houses in Plainville and Smith Center
- March 2010 -- Projected filing of final route siting application with the Kansas Corporation Commission (KCC) for Phase II
- July 2010 -- Anticipated KCC ruling on siting application for Phase II
- Third Quarter 2010 thru Second Quarter 2011 - Right-of-Way Acquisition and Engineering Design
- Fourth Quarter 2011 thru December 2012 -- Line Construction
- June 2013 -- Official in-service date for the entire SKA line. However, ITC is coordinating with Nebraska Public Power District to energize the line by December 2012
Preliminary Route Selection Process
- Preliminary route selection study to identify route alternatives
- Criteria used for preliminary route selection include:
- Total route length
- Number of angle points in the route
- Number of highway and river crossings
- Proximity of residences, schools, churches, and cemeteries within 500 feet of route
- Route length through grasslands, croplands, woodlands, wetlands, and open water
- Avoidance of existing center pivot irrigation systems
- Route selection methodology:
- Establish route study corridor
- Initial desktop route mapping using online aerial photography
- Field review of study corridor and routes
- Environmental evaluation
- Route modifications
- Community Action Group meeting and input
- Public Open Houses
- Provide proposed route for KCC Siting Application
|

|

|
|